M-020–01a – Perform MPS: Master Production Planning (SAP APO)

Execution of MPS, creates a rough-cut capacity production plan to replenish requirements while adhering to master data settings (planning horizon)

Triggers & timing

·         Short/medium range – weekly via batch or as needed interactively via PPDS

·         Long range – daily via batch or as needed interactively via SNP

Key inputs/outputs

Inputs

·          DRP/SCP plan

·          Production Master Data

·          Stock Requirements Situation (/SAPAPO/SNP94)

 

Outputs

·          MPS plan

Batch processing

Task

Description

Tcode

1

Completion of M010 steps

 

2

Part 2 of SNP01 to create SNP planned orders and PFG preqs.

/SAPAPO/SNP01

3

Create Planned orders in PPDS horizon

/SAPAPO/CDPSB1

4

Batch jobs are covered in M-000 Background batch processing.

 

Interactive planning

Task

Description

Tcode

1

SNP Planning

/SAPAPO/SNP94

2

RRP3 Planning

/.SAPAPO/RRP3

Local exceptions

No local exceptions are known.

Reports/forms

Title & Description

Standard (Y/N)